In Due Time
Contractors of all types are notorious for setting impossible-to-keep schedules, thereby disappointing clients and damaging their own credibility in the process.  Sometimes, however, situations arise that require landshapers to shrink their established installation timetables, a necessity that will turn up the heat on even the most accomplished of contractors. For the project profiled in these pages, my clients had something come up that (from their perspective, anyway) necessitated completion of the project much earlier than anyone thought:  They were expecting a baby and insisted that our delivery date should happen before theirs. The challenge we faced with the new timetable - just five months rather than the planned eight - was huge:  It required truly constant interaction and communication with the clients and sub-contractors as well as intensive coordinating and expediting of a mind-boggling number of simultaneous processes - enough to drive us all crazy from time to time, but ultimately a